We use our own and third party cookies to give you the best experience on the services we offer. To accept cookies continue browsing as normal or click Accept. For more information please check our Cookie Policy.




    *mandatory fields

    I confirm that the data submitted in this webform may be used by Knights Brown for answering my enquiry. It may be held on record for business purposes for a period of 12 months.I do not consent to Knights Brown holding my data for business purposes.


    Customer

    Galliard Construction Ltd

    Location

    Deptford Creek, Greenwich

    Value

    £3.5M

    Knights Brown was appointed to construct and install this new footbridge, which will be adopted by Greenwich Borough Council. At high tide, the bridge swings open allowing access for private river traffic and aggregate barges to the ready-mix batching plant.

    The main bridge was pre-fabricated off-site with our project team coordinating and overseeing the fabrication process. The structure consists of sculptural, externally painted weathering steel plate with folded steel plates concealING a 9m backspan containing a 120 tonnes steel counterweight to balance the 44m main span as it opens.

    Access restrictions necessitated extensive planning of the construction sequence and delivery of the prefabricated sections. The main spans were transported by road in three pieces and assembled on the river bank.

    The mast comprises a pair of flat, 40mm thick plates separated by inclined plate stiffeners, which creates an open and transparent structure that acts like a Vierendeel strut in compression. The four-span steel approach structure also uses thick plates in compression with the piers fabricated from single plates.

    A high degree of engineering complexity was successfully managed by the project team including the provision of a sheet piled cofferdam installed on an inter-tidal terrace. This also acted as a piling mat for CFA piles, and significant amounts of back-propping to the basement, to provide adequate support for the 300T crane and construction traffic required to complete the works.

    our sectors

    Site staff were pleased to have had Knights Brown on the team, they were proactive from day one to the end towards potential issues and responsive to a changing site environment for works.

    - David Sheldon, Cummins

    Overall a successful project with good management of the work. Site team asked questions rather than made assumptions which was good. Good communication. Would (and have) recommended Knights Brown for other projects.

    - Chris Clark, Colin Toms & Partners

    This complex and challenging project was a collaborative undertaking from the outset. Combining two projects was inspirational, saving not only money but diverting 22,000m3 from landfill. Some extremely innovative tools and methods were used to demolish the pier, recover material and to achieve the lowest environmental impact on one of the most environmentally designated places in the UK.

    - London and South East Constructing Excellence Awards judging panel on Phase 2 of the North Portsea Island CFERM