We use our own and third party cookies to give you the best experience on the services we offer. To accept cookies continue browsing as normal or click Accept. For more information please check our Cookie Policy.




    *mandatory fields

    I confirm that the data submitted in this webform may be used by Knights Brown for answering my enquiry. It may be held on record for business purposes for a period of 12 months.I do not consent to Knights Brown holding my data for business purposes.


    Customer

    Wärtsilä Energy Solutions

    Location

    Brigg Power Station, Scunthorpe, North Lincolnshire

    Value

    £1.3m

    Construction of a 50MW STOR on a live power station near Scunthorpe including transformer foundations with 8m high blast walls, radiator foundations and new roads and drainage.

    SUMMARY OF WORKS AND SERVICES UNDERTAKEN

    • The construction of 8 metre high concrete blast walls for a 132kv transformer
    • Working on a small site in close confines with numerous other contractors – over 100 operatives
    • Concrete pours of over 400m3

    The project involved working in proximity to a live Centrica power plant and in some cases interacting with the power plant side. The first task was to fill the site to1.8m to provide a suitable piling platform in order to install 40 CFA 600mm diameter piles.

    On completion of the piling we installed over 1,000m of cable conduit and 300m of stainless steel oily water pipe in specific locations excavating in-between piles. We then reduced the level of the piling platform until we reached formation level in section so we were able to crop piles and install a blinding layer.

    The concrete foundations for the main powerhouse structure had a complicated steel reinforcement design with five engine foundations acting independently to the main foundation. The main slab had over 400m3 of concrete, which was poured in a single day using two 52m concrete pumps and completed with a power float finish.

    The main power house building was completed on schedule and allowed the steel erection contractor to progress their works. We also constructed a 40m x 16m bunded radiator foundation in an area that required additional works to remove all the previous power plant structures (i.e. oily water collection pit, asphalt turning areas, cable culverts).

    A transformer foundation was also constructed requiring 8m high blast walls to three sides and concrete plinths to position the transformer on arrival. Two smaller transformer foundations were constructed that required 4m high blast walls in another area of the site.

    Other small items included:

    • Cable pulling pit
    • Oily water collection pit
    • Lube oil tank slab
    • Fire water tank foundation
    • Fire water container foundation
    • Fire water pipe installation
    • Black start unit foundation
    • Over 100 pipe support foundations
    • Installation of 600 tons of decorative gravel
    • Kerb and asphalt works

     

    our sectors

    Site staff were pleased to have had Knights Brown on the team, they were proactive from day one to the end towards potential issues and responsive to a changing site environment for works.

    - David Sheldon, Cummins

    Sites are always very well presented. First impressions count and if a site looks well organised and clean when you arrive then generally this is applied throughout the management of the projects. Indeed, all five projects I am Cummins PM for, have been managed to a high standard and equally the safety records and standards are very good.

    - Iain Brooks, Cummins