We use our own and third party cookies to give you the best experience on the services we offer. To accept cookies continue browsing as normal or click Accept. For more information please check our Cookie Policy.




    *mandatory fields

    I confirm that the data submitted in this webform may be used by Knights Brown for answering my enquiry. It may be held on record for business purposes for a period of 12 months.I do not consent to Knights Brown holding my data for business purposes.


    Customer

    Enercon

    Location

    County Donegal, Republic of Ireland

    Value

    £0.176m

    Buncrana wind farm is located on Clonglash Hill, approximately 5km east of Buncrana. The contract was to build a single E44 wind turbine foundation and a single E82 wind turbine foundation, both with associated drainage and lightening protection.

    The construction of the E44 comprised excavation to formation, where a geotechnical engineer would inspect the formation to determine suitability. It was deemed necessary to excavate down a further 350mm to find a suitable formation. Once good ground was discovered, the levels were brought up to formation level by compacting imported stone in layers to achieve the specified foundation level as per the planning conditions.

    Once level, the works progressed as standard where the ducts were installed and a 100mm blinding layer was laid, followed by steel fixing and installation of lightening protection and fixing of the shutters ready for the concrete pour. Once the concrete was poured as per Enercon’s guidelines and the concrete had cured for at least 48 hours, the shutters were stripped and the foundation inspected for honeycombing and surface cracks. Once the inspection was passed, drainage was installed and the foundation backfilled.

    The construction of the E82 was very similar with the exception of the ground conditions. We encountered hard rock in the excavation and had to break out approximately 1000m3 of rock. Following achieving formation level the formation was inspected by the geotechnical engineer. Once the formation had been accepted, construction of the base continued as per the E44.

    our sectors

    Sites are always very well presented. First impressions count and if a site looks well organised and clean when you arrive then generally this is applied throughout the management of the projects. Indeed, all five projects I am Cummins PM for, have been managed to a high standard and equally the safety records and standards are very good.

    - Iain Brooks, Cummins

    Site staff were pleased to have had Knights Brown on the team, they were proactive from day one to the end towards potential issues and responsive to a changing site environment for works.

    - David Sheldon, Cummins