We use our own and third party cookies to give you the best experience on the services we offer. To accept cookies continue browsing as normal or click Accept. For more information please check our Cookie Policy.




    *mandatory fields

    I confirm that the data submitted in this webform may be used by Knights Brown for answering my enquiry. It may be held on record for business purposes for a period of 12 months.I do not consent to Knights Brown holding my data for business purposes.


    Customer

    Confidential

    Location

    Gloucester

    Value

    £0.437m

    Knights Brown was contracted to construct a 20MW Short Term Operating Facility (STOR) at Bristol Road, Gloucester. Our client is a global provider of power generation systems, components and services in standby power, distributed power generation, as well as auxiliary power in mobile applications to meet the needs of a diversified customer base.

    The natural gas powered 20MW peak demand power facility was to provide power to the National Grid with a quick start-up time (under two minutes).

    The scope of works included the excavations for a new gas main, concrete slabs for the generators, transformers and switch gear, perimeter access roads and drainage for the facility including an oil separator tank, attenuation tanks and a final connection into the Severn Trent sewer via a flow control restrictor @ 5l/s.

    We were also responsible for the provision of substation requirements, inclusive of switchgear arrangements and mechanical fit out, including ducting and connection to the grid.

    The original programme of works allowed for the civil engineering works to be completed ahead of the containerized Genset delivery. We were asked early on to change our sequence of works to allow for the generators to be sited before drainage, roads and fences could be erected, this gave more space and allowed the use of smaller cranes for unloading, significantly reducing costs (350t crane in lieu of 750t crane).

    Knights Brown undertook the role of main contractor throughout the installation and commissioning stages of the project.

    our sectors

    Site staff were pleased to have had Knights Brown on the team, they were proactive from day one to the end towards potential issues and responsive to a changing site environment for works.

    - David Sheldon, Cummins

    Sites are always very well presented. First impressions count and if a site looks well organised and clean when you arrive then generally this is applied throughout the management of the projects. Indeed, all five projects I am Cummins PM for, have been managed to a high standard and equally the safety records and standards are very good.

    - Iain Brooks, Cummins